Broad Street Public Realm Improvements 

Following on from the recent pedestrian improvement works in New Cut and King Street, there is now the opportunity to improve the public realm on Broad Street, for everyone who lives, visits, works, shops or runs businesses in the heart of St Helier.

The project aligns with the Government’s Common Strategic Plan (CSP) and our commitment to revitalise town, along with the improvements St Helier’s infrastructure has already seen.

This blog page is for progress updates and images so Islanders can follow along with the project.

If you’d like to learn more about the vision and timeline, visit our Public Realm website: Broad Street | Public Realm

Phase one of the work is nearing completion with all granite paving works expected to be finished by the end of this week.

Over the next few weeks, until the end of this phase, the introduction of planting and fresh topsoil to the new planters, installation of street furniture such as benches, bin and decorative lighting together with general site clearance and final cleaning, will be carried out.

Jersey Water will shortly recommence their programmed upgrades to water mains and valves at the Broad Street, Bond Street and Conway Street junction, as well as along Broad Street towards Charing Cross.

Newly installed granite street furniture

New Honey Locust ‘Skyline’ trees have been planted on Broad Street using engineered tree cells which will allow their roots to grow without damaging our infrastructure. These trees are a very pretty and thorn-less variety that copes well in hard areas. Its feathery foliage turns a magnificent golden yellow in the Autumn months. The Minister for Infrastructure, Connetable Andy Jehan gave a helping hand!

New trees being planted in Broad Street by Connetable Andy Jehan

In the last few days the tree next to the Blue Note Bar has been relocated to Pont Marquet Country Park by a specialist team. This is because it was limited by the environment and the planter it was in previously. This relocation gives the tree a chance of a new life and frees up space for the planting of two new trees within tree cells – an underground structure that provides space for the soil without compacting it, allowing trees to thrive for generations to come.

The team have also been working on installing bespoke granite furniture with planting to create a welcoming space where Islanders can sit and enjoy their surroundings.

Relocated tree and street furniture

Work on the Broad Street public realm scheme restarted in early January 2026 after the Christmas break. Granite paving on the northern side of the site, including the areas around the old toilet block and the obelisk, has now been completed. The team has begun the next phase, which focuses on paving the central thoroughfare. This includes infilling granite surfacing between the new kerb lines. 

Newly installed granite paving on the northern side of the site

As 2025 draws to a close, we’re pleased to share that work on Broad Street is progressing well and remains on schedule. 

Over recent weeks, large sections have been transformed with new granite paving, including the footway around the historic toilet block and the obelisk. This high-quality finish reflects the character of Broad Street as well as staying in keeping with other Public Realm Improvements across Town. Other key features of the new public space are already in place such as street lighting, including floor lighting, which is now operational.  

As we head into the festive season, activity on site has paused until 5 January 2026. We’d like to thank everyone living, working, and trading nearby for their patience and support throughout the project so far. Your cooperation is helping us deliver a space that everyone can enjoy. From all of the team, we wish residents, businesses, and visitors a very Merry Christmas and look forward to continuing the improvements in the new year. 

Newly installed granite paving and street lighting

We have now finished the advance works and entered the next phase, phase one of the public realm works. A key feature of this phase is the introduction of engineered tree cells which will support the planting of two new trees. These cells provide space for the soil underneath the suspended pavement without compacting it, allowing the roots to grow freely without damaging any surrounding infrastructure.

Along with the preparation for the new trees, the team has also begun installing the granite paving, both of which will contribute to transforming Broad Street into a charming and vibrant public space.

Installation of tree cells and granite paving

The advance works are now complete and infrastructure surveyors have visited the site to set out the arrangement for the upcoming granite paving.

What to expect next: First, noise suspension barriers will be put up around the site to minimise disruption. Then, works to remove the existing road and pavements will begin, preparing the site for the beautiful granite paving, street furniture and the planting of two new trees. Pedestrian access will continue to be maintained.

Completed advance works

Works are continuing to progress well with street lighting upgrades in the Phase 1 area having been undertaken, and the installation of both the new drainage system and the new water main.

In the coming weeks, pedestrian walking routes will temporarily be moved out into the closed section of the road so drainage and water connections can be made to the relevant buildings. These works will be conducted in small sections so pedestrian access into properties is maintained. The site will then be cleared in preparation for the granite paving works.

Further updates to follow.

Reinstated trenches

Phase 1 advance works are progressing well and remain on schedule to finish by early October, preparing the site for the rest of Phase 1. Installation of the drainage system and replacement of the freshwater main has begun, working with Jersey Water and their contractor Jayen to help future proof the underground infrastructure and prepare for the following improvements.

Being in such a historic busy and area brings its own set of challenges. To start, trenches of up to 2 metres deep are required to allow proper drainage connections and to intercept existing outlets, deep enough to reach sand below! Next, engineers need to navigate the existing congested underground infrastructure including pipes, cables and tree roots that need protecting. These works will provide a reliable water supply for the future and reduce the risk of localised flooding during periods of heavy rain. Upgrading these systems now minimises future disruptions once the following Public Realm improvements begin.

Thank you for your continued patience and support.  

Freshly dug trenches

New Public Realm Improvement and Investing in Jersey banners